LEAD TIME:
June 2016 – September 2016
INVESTOR:
ASC WORKERS DARIUSZ KŁAPIŃSKI
CONTRACTORS:
ATLAS WARD POLSKA SP. Z O.O.
SCOPE OF IMPLEMENTATION:
- Mechanical ventilation system for a hall with a total capacity of 150 000 m3/h
- Mechanical ventilation system in an office building
- Cold, hot and circulation water installation
- Fire-fighting system (hydrant)
- Technological heat installation
- Central heating installation
- Gas boiler room with a capacity of 160kW
- Multi-Split air conditioning installation
- Sanitary sewerage installation
- Gas installation